Building new generation facilities to support the clean energy transition.
The right mix of energy resources in the right locations can help reduce reliance on fossil fuels and drive a cleaner resource mix in future years. PGE continues to show progress toward our 2030 emissions target by adding significant amounts of clean energy resources to our portfolio. PGE’s All-Source Request for Proposal is a transparent, competitive process by which interested developers submit detailed project proposals for consideration as we continue to work to decarbonize Oregon’s power supply.
PGE began work on the 2025 RFP while we continued to engage in contract negotiations with projects shortlisted in the previous effort, the 2023 RFP. Reflecting continuing needs for new resources, the 2025 RFP will seek the next tranche of renewable energy and capacity resources. These may include solar, wind, lithium-ion battery storage, and hybrid (renewable + storage) projects located within the state of Oregon and in the region more broadly.
2025 All-Source RFP final documents
Included below are PGE’s final documents for the 2025 All-Source RFP issued July 31, 2025.
Supporting Documents
2025 All-Source RFP draft documents
Included below are PGE’s draft documents for the 2025 All-Source RFP as filed April 17, 2025 with the OPUC and updated on June 24, 2025.
Bid Form Draft - This is the final bid form from the 2023 RFP. The 2025 bid form will likely be similar, but please do not use this file for 2025 RFP purposes.
Included below are redlines of relevant documents.
RFP Schedule
In partnership with OPUC Staff and Stakeholders, PGE has developed the following schedule. The RFP schedule is designed to make timely progress toward PGE’s capacity needs and HB 2021 compliance requirements and is subject to change based on regulatory timing. PGE will update the schedule to reflect any timing changes.
March 4, 2025 – Commission approves PA Consulting to serve as IE.
March 17, 2025 – Public workshop in advance of PGE’s draft.
April 17, 2025 - PGE submits final draft Renewable RFP to OPUC for approval.
July 31, 2025 - PGE issues Final RFP.
August 7, 2025 - Post-issuance bidder conference.
August 13, 2025 – Notice of Intent to Bid due.
August 28, 2025 – Benchmark bids due.
October 1, 2025 — All remaining bids due.
November 13, 2025 - Initial shortlist identified.
November 26, 2026 – Best and final price update.
February 4, 2026— PGE submits request for acknowledgment of final shortlist to OPUC.
Q2/Q3 2026 – Final contracts executed with winning Bidders as applicable.
*These dates are subject to change depending on the quantity and complexity of bids received and should circumstances require.
_____________________________
Dates subject to change.
Rev. 7/31/2025
2023 All-Source RFP final documents
Included below are PGE’s final documents for the 2023 All-Source RFP issued February 2, 2024.
2023 All-Source RFP Main Document
Appendix G: Renewable Resource and Storage Capacity Form PPA
Appendix S: Renewable Power and Storage Capacity Purchase Agreement Form Term Sheet
Appendix S: Renewable Power and Storage Capacity Purchase Agreement Form Term Sheet (MS Word)
Included below are redlines of the final issued term sheets and form contracts:
2023 All-Source RFP draft documents
Included below are PGE’s draft documents for the 2023 All-Source RFP as filed May 19, 2023 with the OPUC.
2023 All-Source RFP Main Document
Appendix G - Renewable Power and Storage Capacity Purchase Agreement Form
Bid Form Draft - This is the final bid form from the 2021 RFP. The 2023 bid form will likely be similar, but please do not use this file for 2023 RFP purposes.