PGE projects in your area

Central service area
Goose Hollow Underground Project
We’re replacing aging distribution lines and substation equipment and placing portions of the system underground to help reduce local outages and strengthen the grid.
Harborton Reliability Project
This project will use advanced conductor technology to upgrade about a quarter mile of existing transmission line and build an additional quarter mile of line with two new poles within an existing transmission corridor, in utility right-of-way on the north edge of Forest Park. It will increase transmission capacity and enhance system safety and reliability.

East service area
Springwater Cazadero Grid Modernization Project
We’re replacing 32 miles of aging transmission towers from south of Estacada to Gresham and into Southeast Portland. Work will continue through 2029 to improve safety and reliability.
Summit-Summit 13 — Mt. Hood Undergrounding Project
We’re placing about six miles of distribution power lines underground near Government Camp to help reduce wildfire risk and improve service reliability in the area. Work is planned during the summer months of 2026 and 2027 and may result in temporary traffic or access impacts while construction is underway.

South service area
Warm Springs Power Pathway
This project will upgrade an existing 99-mile transmission line to expand capacity and address critical transmission constraints. It will help deliver more electricity generated east of the Cascade Mountains to population centers such as Portland and Salem.

West service area
Horizon-Keeler #1
We’re upgrading about 1.5 miles of transmission line in Hillsboro to increase capacity and improve system reliability for the growing region. Construction is planned for Spring 2026, with most work happening at night to reduce traffic impacts along U.S. highway 26 between exits 57 and 67.
Tonquin Project
We built a new substation and are upgrading 11 miles of transmission line to create a backup path for electricity. This improves resilience, strengthens reliability and supports continued growth in the area.
Westside Upgrade Project
We’re upgrading lines and poles along 15 miles of transmission corridor between Sherwood and Beaverton to relieve constraints, adapt to changing energy patterns and stabilize the system.


